Coleville/Kerrobert, Saskatchewan – Waterflood Injection Program

Numerous projects from 2013 to 2015

  • Directional boring daisy-chained well sites
  • Tie-ins from well-head to header systems
  • Fabrication/installation of modular piping skids

Emulsion collection systems

  • Multi well-pad set-ups
  • Directional boring daisy-chained well sites
  • tie-ins from pipelines to facilities

Facility upgrades/Refurbishing

  • Integrity based piping replacement
  • satellite facility construction
  • cutting/capping piles
  • setting building modules
  • heat exchanger installs
  • compressor install
  • flare stack install
  • custom pipefitting

Beaumont, Alberta – Waterflood Program

2013 Water Flood

  • Phase 1 (May 2013): 11.5km of 3″ FP
  • Phase 2 (July 2013): 12.1km of 3″ FP

2014 Water Flood

  • Phase 1 (May 2014): 11.2km of 3″ FP
  • Phase 2 (July 2014): 10.4km of 3″ FP
  • Phase 3 (August 2014): 17.9km of 3″ and 4″ FP

2015 Water Flood

  • Phase 3A (January to March 2015): 27.6km of 3″ and 4″ FP

Module skid #1     size 40 x 40

Module skid #2     size 54 x 20

Module skid #3     size 54 x 20

Directional Drilling

Horizontal Directionally Drilling (HDD) has proven itself over the last few years to be a very effective technique for the installation of pipelines and other utilities in sensitive or congested areas.

Directional Drilling

Pipeline Integrity

At BPC Services LTD we provide cost effective solutions for integrity management programs on regulated pipelines that will ensure regulatory compliance and public safety.

Pipeline Integrity

Fabrication

Our facilities division at BPC Services Ltd presently offer construction services that include both “Shop Fabrication” and “Field Facility Activities”.

Fabrication